Warszawa, mazowieckie. Scope: insulating the roof slopes and the area around the wall plate. Area approximately 168 m²; insulation: open-cell foam.
The project included silverFoam Ag 40 spray insulation in a single-family house with an attic in Warsaw, Masovian Voivodeship. The work focused on proper preparation of the substrate, selection of PUR foam and ensuring the continuity and tightness of the insulation. After completing the application, a quality control of the work performed was carried out.




Illustrative photos.
Scope of work
Parameters
- Working area: approximately 168 m².
- Type of insulation: open-cell foam.
- Specified layer thickness: 25 cm.
- Main scope: insulating the roof slopes and the area around the wall plate.
Project challenge
The most important challenge was to tightly close the insulation with a complex arrangement of rafters and collar beams. Before spraying, the moisture content and stability of the substrate, access to construction details and places where thermal bridges could have occurred were verified. Thanks to this, the foam application was planned in such a way as to maintain the continuity of the insulation and limit subsequent repairs.
Application process
Work began by protecting windows and doors, building services and finishes. Foam was then applied in layers, checking that it expanded evenly and that the junctions at the wall plate, rafters, floor structure and service penetrations were continuous. After application, the surface was visually inspected and the critical areas were filled in before the property was handed over to the client.
Outcome for the client
After completing the work, the attic received an even, tight layer of insulation, ready for further lining. The investor also received recommendations regarding further stages of work, especially ventilation, lining and documenting the layers before closing them.
Key points to remember
- A good project starts with checking the substrate and the scope of work, rather than with spraying itself.
- The details matter most: corners, roof-slope junctions, service penetrations and areas around structural elements.
- Photographs taken during the work are useful for final inspection and acceptance and for the later finishing stages.