Toruń, Kuyavian-Pomeranian Voivodeship. House in developer's standard, working area 127 m². The work was performed by silverFoam Certified Contractor.
On construction sites in the developer's condition, insulation is rarely an independent task. It follows a set sequence of stages, each of which has its own deadline and each one waits for the previous one. First, water and electrical installations, then wet works, i.e. plasters and floors, then insulation, and finally plasterwork and painting. If one link falls out, all subsequent links move.
In this project, the window for insulation work was two days. The plasterboard team was scheduled to start on Thursday.

Illustrative photos.
Scope of work
Parameters
- Working area: 127 m².
- Type of insulation: open-cell silverFoam Ag40 foam.
- Specified layer thickness: 25 cm.
- Main scope: installing framing hangers and insulating the roof slope before plasterboard lining.
What must be agreed before arriving on site
The contractor visited the site before the work began to verify three things.
Firstly, moisture content. Plasters and floors introduce a large amount of water into the building, which evapourates into the interior for weeks. Spraying is performed only when the wet works are dry and the moisture content of the structural wood is within the permissible range. The type and tightness of the membrane and the patency of the covering ventilation were also checked.
Secondly, the completeness of the previous stages. All water, electrical and ventilation routes must be laid and approved before spraying, as adding cables after application means disturbing the insulation layer.
Thirdly, the layout of the framing for the boards. This was agreed with the client and the finishing team before arriving on site, as it determined the organisation of the entire application.
Hangers before spraying
The contractor installed hangers for the future plasterboard framing before spraying, bringing them to a height corresponding to the target 25 cm of foam.
The solution offers three benefits at once. The insulation reaches its full planned thickness, not just what fits between the rafters. The foam covers the entire length of the hangers, so the mounting does not create a thermal bridge. The construction team finds ready installation points in one plane and starts working without marking out or cutting the insulation layer.
Application
The woodwork, installations and finishing elements were secured, and then sprayed in layers with control of the uniformity of foam growth.
Attention was paid to the junctions at the wall plate, rafters, floor structure and service penetrations. The layer was brought to the level defined by the hangers, while keeping their ends exposed and ready for the profiles to be screwed on.
After application, the surface was visually inspected and the critical areas were filled in.
What the client received
Attic with a full layer of 25 cm thick insulation and ready-made installation points for the framing. Another team entered the facility and immediately started installing the profiles, without cutting the foam and without any corrections delaying the work. The deadline was met and the construction schedule remained intact.
In addition, photographic documentation of the entire area before lining. This is a material that will be useful not only during acceptance, but also in a few years, when there is a need to run an additional installation or locate a cable under the slab.
The contractor also provided written recommendations regarding the implementation of vapour barriers and construction, to be passed on to the team entering the building.
Key points to remember
- Insulation has its place in the work sequence: after services and wet trades, but before plasterboard lining and painting.
- Plasters and floors must be dry before spraying. Moisture from wet work affects the adhesion and binding conditions of the foam.
- All installation routes must be ready prior to application. Adding cables later means damaging the layer.
- If the rafters are shallower than the required insulation thickness, the framing hangers can be installed before spraying and brought out to the target layer level.
- Photographs of the roof slopes before lining remain the only map of what is beneath the boards.
Why choose a Certified Contractor
Working in a sequence of trades leaves no room for improvisation. A contractor who arrives without inspecting the building beforehand discovers any omissions only on site, where each decision can delay the entire construction schedule by a day.